Hitotsuse Dam and Lake Merako

Hitotsuse Dam is an arch concrete dam standing 130 meters high on the Hitotsuse River system in Saito City, Miyazaki Prefecture. It was built for hydroelectric power generation and supplies water to Hitotsuse Power Station, operated by Kyushu Electric Power. The power station has a maximum output of 180,000 kilowatts. The artificial lake created by the dam is known as Lake Merako.

In addition to its important role in electricity generation and flood control, Hitotsuse Dam is known for its impressive scale and beautiful setting among the surrounding mountains. Its distinctive arched structure and the expansive lake have made it one of Miyazaki Prefecture’s notable sightseeing destinations.

History and Role of Hitotsuse Dam

Hitotsuse Dam was constructed on the Hitotsuse River, which flows through Saito City and neighboring areas, and was completed in 1963. It measures 130 meters in height and 415.6 meters in length. As an arch dam, it is among the largest of its kind in Japan. Its enormous concrete arch creates a striking landscape against the mountains.

The dam has crest gates positioned on the left bank, right bank, and center. These gates allow large volumes of water to be discharged efficiently during floods. The dam therefore serves not only as a source of hydroelectric power but also as an important facility for regulating floods and protecting downstream communities.

Lake Merako and Hydroelectric Power Generation

The reservoir formed by Hitotsuse Dam is called Lake Merako. It has a total storage capacity of 261.31 million cubic meters and a surface area of 686 hectares, making it one of the largest dam reservoirs in Kyushu in terms of water volume.

Water stored in the lake is sent to Hitotsuse Power Station, operated by Kyushu Electric Power, approximately 3 kilometers downstream. The power station has a maximum generating capacity of 180,000 kilowatts. This is the largest output among conventional hydroelectric power stations in Kyushu and plays an important role in supplying electricity to the region.

Materials explaining Hitotsuse Dam and its power-generation system have also been displayed at the power station, where visitors could learn about the facility and its operation in greater detail.

The Dam’s Design and Scenic Beauty

The appeal of Hitotsuse Dam lies not only in its enormous scale but also in the elegant design of its arch structure. Viewed from downstream, the three crest gates positioned across the dam create a balanced composition. The gates on both sides are designed as ski-jump-type spillways, giving the structure a distinctive appearance.

When water is released, the powerful flow combines with the graceful curves of the concrete arch to create an especially impressive sight. The contrast between the massive dam and the surrounding natural landscape makes it an attractive destination for visitors interested in architecture, engineering, and photography.

Selected as One of Japan’s 100 Dams

In recognition of its attractive design and practical functions, Hitotsuse Dam was selected for the Japan Dam Association’s list of the 100 Dams of Japan. This recognition has helped make it a popular destination among dam enthusiasts and photography lovers. The scenery, in which the dam’s distinctive shape blends with the surrounding mountains, is one of its most memorable features.

Attractions Around Hitotsuse Dam

Hitotsuse Dam Observatory

One of the places visitors should not miss is the Hitotsuse Dam Observatory. Located along National Route 219, this viewpoint offers a panoramic view of the dam’s entire arch structure and the landscape on the opposite bank.

On clear days, the view from the observatory is particularly impressive, allowing visitors to appreciate the immense scale of the dam. The scenery around the reservoir also changes with the seasons, so the area offers different views throughout the year.

Herabuna Fishing at Lake Merako

Lake Merako is also an attractive destination for fishing enthusiasts. It is particularly well known as a fishing spot for herabuna, or Japanese crucian carp. The lake has gained a nationwide reputation for its large specimens, sometimes referred to as giant herabuna.

Fish measuring more than 50 centimeters may be caught here, attracting anglers who come to test their skills. Fishing beside the lake offers a peaceful way to enjoy the natural surroundings and the calm atmosphere of this large reservoir.

Sightseeing Around Saito City

Visitors to Hitotsuse Dam can also explore the surrounding attractions. Saito City is home to numerous ancient burial mounds and historic structures, making it an appealing destination for anyone interested in Japanese history.

One particularly important site is the Saitobaru Burial Mounds, a nationally designated Historic Site and one of the largest groups of ancient burial mounds in Japan. Its extensive grounds and beautiful scenery are well worth exploring. Combining a visit to the dam with the historical attractions of Saito City makes for an enjoyable sightseeing route.

The Role and Future of Hitotsuse Dam

Hitotsuse Dam performs several important functions, including hydroelectric power generation, flood regulation, and water-resource management. As a power-generation facility operated by Kyushu Electric Power, it supports a stable electricity supply. During periods of heavy rain, its large storage capacity also helps reduce the risk of flood damage in downstream areas.

The dam is expected to remain important in supporting sustainable energy supplies and the conservation of the natural environment in the region.

Balancing Environmental Conservation and Tourism

The area surrounding Hitotsuse Dam is blessed with a rich natural environment. Efforts are being made to protect this environment while maintaining the area’s appeal as a tourist destination.

As visitor numbers increase, it is important to minimize the impact of tourism on the natural surroundings and promote sustainable ways of enjoying the area. Facilities and activities around Lake Merako, including fishing and hiking routes, are being developed with the aim of allowing tourism and environmental conservation to coexist. These efforts help ensure that visitors can continue to enjoy the area’s beautiful scenery in the future.

History of Hitotsuse Dam

Background and Planning of the Construction Project

Before Hitotsuse Dam was built, several small hydroelectric power stations operated along the Hitotsuse River basin. These included Makiguchi Power Station, with an output of 10,000 kilowatts; Murasho Power Station, with an output of 8,000 kilowatts, later increased to 8,800 kilowatts; Shimoaimi Power Station, with an output of 8,500 kilowatts; and Hitotsusegawa Power Station, with an output of 9,000 kilowatts.

These facilities used either run-of-river systems or regulating reservoirs. Following the rapid growth of electricity demand during Japan’s postwar period of high economic growth, Kyushu Electric Power planned to build a large-scale hydroelectric power facility on the Hitotsuse River. Construction began in October 1959 (Showa 34).

Construction Technology and Progress

In constructing Hitotsuse Dam and Hitotsuse Power Station, Kyushu Electric Power drew on experience gained from the construction of Kamishiiba Dam, completed in 1955, as well as lessons from the catastrophic collapse of the Malpasset Dam in France in 1959.

The project employed advanced construction technology available at the time. Large-scale models were used for hydraulic experiments to optimize the design. Measures were also taken to improve the capacity of the temporary diversion channel, which carried river water past the construction site before the reservoir began filling.

Construction machinery was introduced to reduce the number of workers required. Efforts were also made to improve worker morale, helping keep construction-related problems and criminal incidents to a minimum.

Water storage in the dam began on April 2, 1963 (Showa 38), and Hitotsuse Power Station began operating in June of the same year. However, the construction project also involved a tragic loss of life: 41 workers died during the work. The existing Shimoaimi Power Station and Hitotsusegawa Power Station were closed as a result of the project.

Making Effective Use of Water Resources

On October 25, 2013 (Heisei 25), Hitotsuse Maintenance Flow Power Station began operating. It generates 330 kilowatts of electricity by using the river-maintenance flow, making more effective use of the available water resources.

Hitotsuse Power Station has a maximum output of 180,000 kilowatts, twice that of Kamishiiba Power Station. Excluding pumped-storage facilities, it is the largest conventional hydroelectric power station in Kyushu and ranks tenth in Japan among conventional hydroelectric power stations.

Features of the Hitotsuse Dam Area

Hitotsuse Dam can be reached by traveling northwest along National Route 219, also known as the Merakaido, from Saito Interchange on the Higashi-Kyushu Expressway. The route passes through the central area of Saito City and enters Sugiyasukyo Gorge before reaching the dam.

The dam is equipped with ski-jump-type spillways on both banks and an overflow-type spillway at the center of the crest. These structures are designed to manage the discharge of water from the reservoir.

On the left bank upstream of the dam, there was formerly a Kyushu Electric Power facility called the Hitotsuse Power Station Museum. The museum used models to explain the history of the power station’s construction and the structure of its equipment, including the water turbine generators and selective water intake facilities. However, it closed on March 9, 2014 (Heisei 26), as part of the company’s business-restructuring measures. A local community exchange center opened at the site in June of the same year.

The top of the dam is used as a pedestrian walkway, but access by the general public is restricted. Lake Merako, created by the construction of the dam, became the largest dam reservoir in western Japan at the time. The lake extends approximately 22.5 kilometers from the dam and submerged 5.6 square kilometers of land.

Effects of Dam Construction on the Local Community

Impact on Residents and Compensation Negotiations

The construction of Hitotsuse Dam led to opposition among residents of the former Higashimera Village. Opinions differed among the various districts, but negotiations over compensation with Kyushu Electric Power continued. By 1961 (Showa 36), all districts had ultimately agreed to the construction project.

When the dam was completed and the reservoir filled, numerous homes, agricultural fields, roads, and schools were submerged. The former Higashimera Village consequently chose to merge with Saito City and Kijo Village, now Kijo Town.

Other issues also arose during the project. Miyazaki Prefecture sought the return of public hydroelectric power stations that had been placed under state control during the war, while Asahi Kasei requested compensation because a water intake weir serving one of its private power stations would be submerged. These disputes were also resolved through negotiations.

Hitotsuse Dam and Sugiyasu Dam

Downstream from Hitotsuse Dam is Sugiyasu Dam, another arch concrete dam managed by Kyushu Electric Power. It stands 39.5 meters high and was constructed during the same period as Hitotsuse Dam.

Sugiyasu Dam forms a regulating reservoir that adjusts the water discharged from Hitotsuse Power Station. Rather than allowing the large volume of released water to flow immediately downstream, the reservoir temporarily stores it before it is discharged through Sugiyasu Power Station, which has an output of 11,500 kilowatts.

Construction of Sugiyasu Dam began in 1960 (Showa 35), and Sugiyasu Power Station began operating in March 1963.

Water Turbidity Issues and Countermeasures

Heavy rainfall frequently caused muddy floodwater to flow into Hitotsuse Dam, resulting in turbid water in the reservoir. To address this problem, Kyushu Electric Power installed selective water intake equipment in 1971 (Showa 46). This system makes it possible to draw water from a chosen depth in the reservoir.

When the water becomes turbid, water can be taken from deeper layers, allowing a layer of clearer water to form near the surface. This helps the reservoir recover from turbidity more quickly.

The selective intake system has been improved over time. In 1993 (Heisei 5), it was modified to allow water to be drawn from even deeper layers. In 2002 (Heisei 14), a floating flow-velocity reduction system was installed to prevent turbid water accumulated in the deeper parts of the reservoir from being stirred up into the surface layers.

Additional Measures to Control Turbidity

Turbidity-control membranes have also been installed in rivers flowing into the reservoir. Gravel is regularly added to help prevent sediment carried in by the rivers from accumulating. These measures have contributed to improvements in the water turbidity problem at Hitotsuse Dam.

Information

Name
Hitotsuse Dam and Lake Merako
一ツ瀬ダム・米良湖
Area
Miyazaki Miyazaki city, Miyakonojo, Nichinan
Category
Waterfalls, Lakes, Ponds, Dams

Gallery

Miyazaki city, Miyakonojo, Nichinan

Miyazaki

Category

Area